H. Tighten all of the bolts until they are finger-tight or until they just
begin to move the table sections together. Do not force or over-
tighten the bolts.
I. Repeat steps G and H until the two table sections are completely
drawn together.
J. When all bolts are snug, apply a final torque of 60 pound-feet (80 N-M)
to all bolts using the sequence shown in Figure 2.13.
K. Jack up the assembled table as required to install the remaining
isolators and leveling valves. Install the isolators and valves as
described in Section 2.1.
L. Remove the jack stands and level the table as described in
Section 2.2.
M. Install the air lines and float the table as described in Section 2.4.
19 17 13 11 159 5 1 3 7
20 16 12 10 14 188 4 2 6
(Correct)
(Incorrect)
See CAUTION
Female Table Male Table
Figure 2.13 — Double Bolt Tightening Sequence