Lift from the street to the set up location
If the base allows, the simplest thing is to use a pallet
truck to move the F2120 to the set up location.
NOTE
The centre of gravity is offset to one side (see
print on the packaging).
Approx. 180 kg
If F2120 needs to be transported across soft ground,
such as a lawn, we recommend that a crane is used that
can lift the unit to the installation location. When F2120
is lifted with a crane, the packaging must be undisturbed,
see the illustration above.
If a crane vehicle cannot be used the F2120 can be
transported on an extended sack truck. F2120 must be
taken from its heaviest side and two people are required
to lift F2120.
Lift from the pallet to final positioning
Before lifting remove the packaging and the securing
strap to the pallet.
Place lifting straps around each machine foot. Lifting
from the pallet to the base requires four persons, one
for each lifting strap.
Scrapping
When scrapping, the product is removed in reverse order.
Lift by the bottom panel instead of a pallet!