Installation and Setup
www.nvidia.com
NVIDIA RTX Blade Server DU-09554-001 _v02|15
1.
Place the template so that the bottom of the template rests on the rail lip (or at the
same level as the rail lip).
2.
Install the cage nuts at the positions indicated on the template.
Rail kits attached to Type A racks require two (2) cage nuts installed.
Rail kits attached to Type B racks require four (4) cage nut installed.
Rack shelf installations require four (4) cage nuts installed.
2.4.4.Mounting the RTX Blade Server
Caution Stability hazard — The rack stabilizing mechanism must be in place, or
the rack must be bolted to the floor before you slide the RTX Blade Server out for
servicing. Failure to stabilize the rack can cause the rack to tip over.
CAUTION: The RTX Blade Server weighs approximately 300 lbs, so an equipment lift is
required to safely lift the unit and then accurately align the chassis rails with the rack rails.
1.
Move the RTX Blade Server to the lift.