3-4
2-9. Peaking Balance Adjustment
BOARD MAIN BOARD / SUB2 BOARD
SPEC 3.9v+/-0.1v
Peaking A = Peaking B
TEST Pin 16 of CN1 and EVF Picture
ADJUST RV2 [PEAK-OFFSET]
M.EQ Digital Volt Meter
1. Set the BRIGHT VR to the minimum position, CON-
TRAST VR to the center position and PEAKING VR to
the maximum position.
2. Open the on-screen menu on the camera recorder in
the3:4 mode so that the EVF screen is 4:3.
3. Aim the camera recorder to the registration chart, and
adjust the zoom and focus so that the full-size and
best focus registration chart is displayed on the
screen of the EVF.
4. Adjust RV2 so that the both peaking width A and
B are equal.(Figure.4)
3. Electrical Adjustment
Procedures (AJ-VF20W)
3-1. Power voltage Adjustment
BOARD MAIN BOARD
SPEC 9.5v+/-0.1v
TEST TP2 (Pin 1 of CN3)
ADJUST RV1 [V0-ADJ]
M.EQ Digital Volt Meter
1. Adjust RV1 so that the voltage is within the specifica-
tion.
3-2. V. Hold Adjustment
BOARD MAIN BOARD / SUB1 BOARD
SPEC 48+/-0.5Hz (NTSC)
38+/-0.5Hz (PAL)
TEST TP12 (Pin 4 of CN2)/ MAIN BOARD
ADJUST RV2 [V-HOLD] / SUB1 BOARD
M.EQ Frequency Counter
1. Adjust RV2 so that the frequency is within the specifi-
cation.
3-3. H. Hold Adjustment
BOARD MAIN BOARD / SUB1 BOARD
SPEC 15.73+/-0.05kHz (NTSC)
15.63+/-0.05kHz (PAL)
TEST TP9 (Pin 1 of CN2)/MAIN BOARD
ADJUST RV1 [H-HOLD]/SUB1 BOARD
M.EQ Frequency Counter
1. Adjust RV1so that the frequency is within the specifica-
tion.
3-4. Focus Adjustment
BOARD MAIN BOARD
SPEC 6.0kv+/-0.1kv
TEST Connector between FBT/ Anode Cap
ADJUST RV5 [FOCUS]
M.EQ High Voltage Meter with
High Voltage Prove
1. Aim the camera recorder to the registration chart and
adjust the zoom and focus so that the full-size and
best focus registration picture is displayed on the
screen of EVF.
2. Connect a high volt meter with high voltage prove to the
connector the anode cap and FBT.
3. Adjust RV5 so that the high voltage is within the
specification.
Peaking A
Peaking B
Fig.4 Peaking Balance adjustment