10.2. Refrigerant additional charge
1. Piping installation by standard piping
• At the time of shipment from the factory, this unit is charged with enough refrigerant for an equivalent pipe length of 20 m.
(Refer the following table)
But when the piping length exceeds 20m, additional charge is required according to the following table.
Example:
CU-J14DBE5
In case of 30m long pipe (one way), the amount of refrigerant to be replenished is: (30 - 20) x 20 = 200g
10.3. Position of the centre gravity
Model Name Standard piping specification
Liquid piping
(dia.mm)
Gas piping
(dia.mm)
Gas chargeless
length (m)
Additional gas
volume (g/m)
CU-J14DBE5 6.35 12.7 20 20
CU-J18DBE5 6.35 12.7 20 20
MODEL NAME OUTSIDE DIMENSIONS NET WEIGHT CENTRE OF GRAVITY
WIDTH (mm) DEPTH (mm) HEIGHT (mm) kg X (mm) Y (mm) Z (mm)
CU-J14DBE5 900 320 795 69 560 150 320
CU-J18DBE5 900 320 795 69 560 150 320