EasyManuals Logo

P&B MPR3E5 User Manual

P&B MPR3E5
36 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #28 background imageLoading...
Page #28 background image
14/1/98 Page 26 Issue H
Relay Settings Test Current Nominal Operating Time
THERMAL
t6x = 10
I
FLC
= 0.5 x In
1.0 x In
3.0 x In
100.0 secs
10.0 secs
LOW SET
tI> =1.0
I> = 400% of FLC
4 x In
6 x In
1 sec--**
1 sec-**
HIGH SET
tI> = 0.5
I>> = 700% of In
8** x In
10** x In
0.5 secs
0.5 secs
EARTH FAULT
tIe = 1 sec
Ie =20% of In
0.3 x In
1.0 x In
1 sec
1 sec
Note -**
During starting the low set overcurrent is inhibited and the high set overcurrent is doubled.
If test current is applied to the relay from zero a start condition will be assumed, therefore the
test current must be applied from a running condition i.e. FLC and the trip time measured
from the instant the setting is exceeded.
Recommended Test Equipment - Available through P&B
Single Phase Secondary Injection - Sverker 750
Three Phase Secondary Injection - Freja RTS21
Primary Injection Test - up to 600A = 600 AT
- up to 2250A= ODEN/1x
- above 2250A = ODEN / 2x
Rapid Relay Test
A rapid relay test can be carried out with the relay in normal protective service. The relay test
consists of a check of incoming current values by entering Display Mode 1 and cycling through the
displayed values. This rapid test verifies that the energising and measuring circuits are operating
correctly.
Reset of Thermal capacity ( for test )
During testing, the thermal capacity may be reset to zero by removing the auxiliary supply, and then
re-energising the auxiliary supply whilst both the value up and value down buttons are
pressed.
Output Relay Test
By entering the test trip mode as detailed previously in this manual, the output relays may be
operated in a cyclic manor, testing the complete trip circuit.
Phase Rotation Test
This can only be tested with a 3 phase current injection test set with the phases 120° apart. (Single
phase injection will give spurious results.) The feature is only active during a start, therefore a
current higher than 150% FLC should be injected for a period greater than 10 sequence errors in a
row.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the P&B MPR3E5 and is the answer not in the manual?

P&B MPR3E5 Specifications

General IconGeneral
BrandP&B
ModelMPR3E5
CategoryRelays
LanguageEnglish