Fill Cycle
Once the calorimeter is started and the cover is closed, the fill sequence begins.
Figure 3-3
Bucket Fill Flow Diagram
1. The calorimeter checks the bomb ignition circuitry for continuity.
2. The water fill solenoid opens and water is pumped from the internal tank into and through the bucket that
surrounds the bomb. Overflow from the bucket is returned to the closed water tank. Because the jacket and
bucket are both filled with water from the closed water tank, initial equilibrium will be reached quickly.
3. The oxygen fill solenoid is opened and oxygen is added slowly to the bomb to bring its pressure to
approximately 30 atm.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Parr Instrument 6400 and is the answer not in the manual?

Parr Instrument 6400 Specifications

General IconGeneral
BrandParr Instrument
Model6400
CategoryMeasuring Instruments
LanguageEnglish