I. PRELIMINARY INFORMATION
MODEL NO.:
SERIAL NO.:
DATE:
TECHNICIAN:
START-UP CHECKLIST
(Remove and Store in Job Files)
II. PRESTART-UP (Insert check mark in box as each item is completed)
( ) VERIFY THAT ALL PACKING MATERIALS HAVE BEEN REMOVED FROM UNIT
( ) REMOVE ALL SHIPPING HOLD DOWN BOLTS AND BRACKETS PER INSTALLATION INSTRUCTIONS
( ) CHECK ALL ELECTRICAL CONNECTIONS AND TERMINALS FOR TIGHTNESS
( ) CHECK THAT INDOOR (EVAPORATOR) AIR FILTER IS CLEAN AND IN PLACE
( ) VERIFY THAT UNIT INSTALLATION IS LEVEL
( ) CHECK FAN WHEEL, AND PROPELLER FOR LOCATION IN HOUSING/ORIFICE AND SETSCREW TIGHTNESS
III. START-UP
ELECTRICAL
SUPPLY VOLTAGE
COMPRESSOR AMPS
INDOOR (EVAPORATOR) FAN AMPS
TEMPERATURES
OUTDOOR (CONDENSER) AIR TEMPERATURE
RETURN-AIR TEMPERATURE
COOLING SUPPLY AIR
HEAT PUMP SUPPLY AIR
ELECTRIC HEAT SUPPLY AIR
PRESSURES
REFRIGERANT SUCTION
REFRIGERANT DISCHARGE
DB
DB
DB
PSIG, SUCTION LINE TEMP*
PSIG, LIQUID TEMPi-
( ) VERIFY REFRIGERANT CHARGE USING CHARGING CHARTS
* Measured at suction inlet to compressor
1- Measured at liquid line leaving condenser.
WB
WB
35