6CP100/50-10
4-1
SECTION 4: INITIAL SET-UP--MECHANICAL
1. Set up object under test.
2. The area to be used for the test must provide sufficient mechanical and electrical clearances. The
approximate weight of each section is available from the nameplates or the Specification Page.
3. If the unit is to be operated indoors, be sure the floor will be strong enough to support the unit.
If outdoor operation is to be used, the site for the base must be capable of supporting the unit
without any settling that would tilt the assembly.
4. Position the High Voltage Transformer Tank and Control Unit as necessary for operation.
5. Clean entire High Voltage Unit using nothing stronger than ordinary household cleaner to remove all traces
of any surface contamination. This cleaning should also include the High Voltage Electrodes.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Phenix Technologies 600 SERIES and is the answer not in the manual?

Phenix Technologies 600 SERIES Specifications

General IconGeneral
BrandPhenix Technologies
Model600 SERIES
CategoryDiagnostic Equipment
LanguageEnglish