6CP200/100-10
5-2
OPERATIONAL VERIFICATION PROCEDURE
15. Connect high voltage cylinders for parallel operation. (See drawing #763992894.)
16. Move short from 200 kV output to 100 kV output and ground. Repeat step 13. Unit should trip off at
approximately 10 mA.
CAUTION: Do not attempt to check 110% level of current trip under shorted output conditions. Rated
output currents are only available through a capacitive load of sufficient value. Shorted current values
should never exceed 50% of rated currents for the High Voltage Tap being used. If desired to test at 110%
of current rating, the output must be connected to a High Voltage load appropriate to the rated voltage and
current of the test set.
17. Return Voltage Control to Zero. Press HV Off switch. Turn Off Main Power Circuit Breaker on Controls.
END OF OPERATIONAL VERIFICATION TEST!

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Phenix Technologies 6CP200/100-10 and is the answer not in the manual?

Phenix Technologies 6CP200/100-10 Specifications

General IconGeneral
BrandPhenix Technologies
Model6CP200/100-10
CategoryTest Equipment
LanguageEnglish

Related product manuals