Page 15
5. Maintenance
The PPS25 gauges must be well maintained in order to ensure successful operations. There are two
levels of maintenance should be implemented:
Field maintenance
Manufacturer’s maintenance
5.1 Field Maintenance
The following regular maintenance should be implemented before each operation:
Replace the exposed o-rings to protect the gauges from potential damage
caused by the o-ring failure;
Check functionality of the gauges before putting them into well. You can run
a bench test to check if the gauges are in good condition. Or, use the
Diagnostics function by SmartView software to check your gauges (See 4.3
).
Check voltage of battery packs by a PPS battery tester (See 4.5).
The lowest required voltage of single cell battery pack is 3.2V; for dual
cells battery packs, the lowest voltage of battery is 2.6V.
Clean the threads and check for any damage;
Clean the sensor protector.
All threads should be greased after each operation.
5.1.1 Replacing o-rings (Fig. 13)
Apply o-ring grease;
Clean o-ring groove and attach a plastic tube to protect the thread;
As shown in the figure below, use 2 wires to install the o-ring. Ensure the
wires used for this purpose should not damage the o-rings);
Apply o-ring grease to cover the o-rings.
For information about O-rings, please see 5.1.3 for details.
Fig. 13
Before each operation, please inspect all gauges.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the PPS PPS25 and is the answer not in the manual?

PPS PPS25 Specifications

General IconGeneral
BrandPPS
ModelPPS25
CategoryMeasuring Instruments
LanguageEnglish