91RAV505 - RAV506 - RAV507
RAV508 - RAV509 - RAV510
0580-M020-0
VERIFICHE DI PRIMA INSTALLAZIONE - SOLLEVATORE TIPO RAV ...
N° MATRICOLA ...
R Verifica distanza delle pedane dai muri dove è installato (consigliato 1500 mm)
> 700 mm
R Verifica distanza interna pedane
> 800 mm
R Verifica altezza di sollevamento dal piano pavimento a piano pedane H
> 1825 mm (soll. incassato)
R Verifica altezza di sollevamento dal piano pavimento a piano pedane H > 2090 mm (soll. a pavimento)
R Livellamento base mettendo eventualmente spessori
R Serraggio tasselli fissaggio basi al pavimento
R Serraggio tubi idraulici da centralina a basi
R Controllo livello olio centralina
R Controllo allacciamento rete e collegamento cavi
R Attivazione sicurezze
R Collegamento impianto pneumatico
R Spurgo aria impianto idraulico
R Verifica comandi elettrici (l'interruttore generale, pulsante salita, pulsante discesa)
R Controllo funzionamento valvola di riallineo pedane e allineamento delle stesse
R Controllo inserimento arpioni su cilindri
R Controllo funzionamento pressostato
R Controllo funzionamento cicalino
R Controllo tempi di salita e discesa a pieno carico
DATA
FIRMA INSTALLATORE FIRMA UTILIZZATORE
INITIAL INSTALLATION INSPECTIONS - LIFT TYPE RAV ...
SERIAL NUMBER...
R Check distance of platforms from any walls (recommended value 1500 mm)
> 700 mm
R Check internal platform distance > 800 mm
R Check elevation height from floor to platform surface H > 1825 mm (recessed lift)
R Check elevation height from floor to platform surface H
> 2090 mm (floor lift)
R Base levelling, if necessary by placing shims
R Tighten the anchors securing the bases to the floor
R Tighten the hydraulic pipes between the control unit and bases
R Check oil level in control unit
R Check mains and cable connections
R Start safety devices
R Pneumatic system connection
R Bleed air from hydraulic system
R Check power controls (main switch, up button, down button)
R Check operation of platform realignment valve and platform alignment
R Check engagement of safety pawls on cylinder
R Check pressure switch operation
R Check buzzer operation
R Check up/down times with full load