FINAL STEPS
BOLTS: ENSURE ALL BOLTS HAVE BEEN TIGHTENED SECURELY.
GROOVES: CONFIRM THE CABLES ARE SEATED WITHIN THE PULLEY GROOVES.
CABLE RUBBING: PULL THE CABLES TO CHECK FOR EXCESS RESISTANCE. IF IT
SEEMS THE FRICTION IS TOO HIGH, MAKE SURE THE CABLES ARE NOT RUBBING
ANYTHING. A RUBBING CABLE WILL PEEL THE CABLE JACKET AND REQUIRE
REPLACEMENT.
GUIDE RODS: CLEAN THE GUIDE RODS. THEN APPLY SILICONE SPRAY TO THE
GUIDE RODS.
TEST: RUN THE MACHINE THROUGH THE FULL RANGE OF MOTION. ROTATE THE
PULLEY BRACKETS ON TOP OF THE WEIGHT STACK SO THE CABLES DO NOT
RUB THE UPPER CROSSMEMBERS. ONCE POSITIONED CORRECTLY, TIGHTEN
THE SET SCREWS WITH A 4MM ALLEN WRENCH (SEE IMAGE BELOW).
1.
2.
3.
4.
5.
SET SCREW
4MM ALLEN HEAD
X2 PER BRACKET