28 EB 8546 EN
Measures for preparation
4 Measures for preparation
After receiving the shipment, proceed as fol-
lows:
1. Check the scope of delivery. Compare
the shipment received with the delivery
note.
2. Check the shipment for transportation
damage. Report any transportation dam-
age.
4.1 Unpacking
Do not remove the packaging if the supply
pressure regulator is to be transported to
another location or kept in storage.
Before mounting the supply pressure regula-
tor, proceed as follows:
1. Remove the packaging from the supply
pressure regulator.
2. Dispose of the packaging in accordance
with the valid regulations.
Risk of damage to the supply pressure
regulator due to foreign particles entering it.
Do not remove the protective lm until
immediately before mounting.
4.2 Storage
Risk of damage to the supply pressure
regulator due to improper storage.
Observe the storage instructions. Contact
SAMSON, if need be.
Storageinstructions
− Protect the supply pressure regulator
against external inuences (e.g. impact,
shocks, vibration).
− Do not damage the corrosion protection
(coating).
− Protect the supply pressure regulator
against moisture and dirt. In damp
spaces, prevent condensation. If
necessary, use a drying agent or
heating.
− Pack the supply pressure regulator in air-
tight packaging.
Note
NOTICE
!
NOTICE
!