EasyManua.ls Logo

Schier GB2 User Manual

Schier GB2
9 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
Page #1 background imageLoading...
Page #1 background image
INSTALLATION GUIDE
Model #GB2 35/50 GPM Grease Interceptor
For Indoor Use
Contents
Special Precautions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Geing to Know the GB2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
On the Floor Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4-6
Buried Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7-9
Part #: 057-1260-02
Find these instructions online at: schierproducts.com/pages/gb2
Question and Answer IconNeed help?

Do you have a question about the Schier GB2 and is the answer not in the manual?

Schier GB2 Specifications

General IconGeneral
BrandSchier
ModelGB2
CategoryPlumbing Product
LanguageEnglish

Summary

Special Precautions for Grease Interceptor Installation

General Installation Instructions and Codes

Follow all instructions and local codes; installation by licensed plumber.

High Temperature Water Handling

Use tempering valve for water over 140°F to prevent damage and voiding warranty.

Indoor Installation Flow Regulation

Regulate sink drain flow to prevent floor water overflow when installing indoors.

High Water Table Installation Guidance

Install in watertight vaults or use anchor kits in high water table areas to prevent damage.

Hydrostatic Slab Installation Requirements

Enclose interceptors in watertight vaults when installed under hydrostatic slabs.

GB2 Grease Interceptor Component Overview

GB2 Unit Parts Identification

Detailed diagram and list of all components of the GB2 grease interceptor.

On the Floor Installation Guide

On-Floor Installation Precautions and Warnings

Critical warnings and safety steps before beginning on-floor installation.

Water Tightness Testing Procedure

Steps to cap connections and fill the unit to test for leaks.

Outlet Diffuser and Plug Configuration

Instructions for configuring the outlet diffuser and installing cleanout plugs.

Flow Control Calibration for GB2

Adjusting the internal flow control plate for desired flow rate (35 or 50 GPM).

Connecting Inlet and Outlet Piping

Guidance on connecting piping to the interceptor, including vent requirements.

Piping System Wet or Air Testing

Performing required wet or air tests on the installed piping per local codes.

Buried Installation Guide

Buried Installation Precautions and Warnings

Essential safety warnings and guidelines specific to buried interceptor installations.

Buried Unit Water Tightness Test

Procedure to ensure the interceptor is watertight before backfilling.

Buried Outlet Diffuser and Plug Setup

Steps to configure the outlet diffuser and install cleanout plugs for buried units.

Flow Control Calibration for Buried Units

Calibrating the flow control based on installation height for buried GB2 units.

Piping Connections for Buried Systems

Connecting pipes to the interceptor and preparing for burial, including excavation.

Backfilling and Finished Grade Procedures

Guidelines for proper backfilling with aggregate and concrete pad for finished grade.

Related product manuals