Receiving, handling and storage
Lifting type SDV6 distribution circuit
breaker with crane
Recommended lifting of type SDV6
distribution circuit breakers is by means of
cables connected to an overhead crane.
The cables are connected to the lifting lugs
on the top of the type SDV6 distribution
circuit breaker as illustrated in Figure 2:
Lifting type SDV6 distribution circuit
breaker with crane on page 10. A crane
with sufficient height should be used so
the load angle on the lifting cable will be
50° approximately when viewed from the
front or rear.
Storage
When it is necessary to store a type SDV6
distribution circuit breaker in an area
exposed to the weather or under humid
conditions, energize the space heaters
provided and make certain that any vents
are uncovered to allow air to circulate. If at
all possible, install the type SDV6
distribution circuit breaker at the
permanent location even though it may be
some time before the equipment is used. It
is also recommended that the type SDV6
distribution circuit breaker receive periodic
inspection during storage.
Access to the heater circuit is gained by
opening the door to the low-voltage
compartment. Refer to the wiring diagram
drawing for space heater circuit
connections. Lubricate hinges and other
moving parts.
11

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens SDV6 and is the answer not in the manual?

Siemens SDV6 Specifications

General IconGeneral
BrandSiemens
ModelSDV6
CategoryCircuit breakers
LanguageEnglish

Related product manuals