Installation
Manual spring charging check
1.    Insert the manual spring charging 
crank into the manual charge socket 
as shown in Figure 6: Low-voltage 
compartment on page 19. Turn the 
crank until the spring condition 
indicator shows the closing springs 
are charged, and remove the spring 
charging crank from the socket.
2.    Repeat the spring discharge check 
presented on page 18.
3.    Verify the springs are DISCHARGED 
and the circuit breaker primary 
contacts are OPEN by observing the 
indicator positions.
As-found and vacuum check tests
Perform and record the results of both the 
as-found insulation test and the vacuum 
check high-potential test. Procedures for 
these tests are described in the 
maintenance section of this instruction 
manual beginning on page 25.
Automatic spring charging check
Note: A temporary source of control power 
and test leads may be required if the 
control power source has not been 
connected to the circuit breaker. Refer to 
the specific wiring information and rating 
label for your circuit breaker to determine 
the voltage required and where the control 
voltage signal should be applied. When 
control power is connected to the circuit 
breaker, the closing springs should 
automatically charge if the control power 
disconnect (refer to Figure 6: Low-voltage 
compartment on page 19) is closed.
The automatic spring charging features of 
the circuit breaker must be checked. 
Control power is required for automatic 
spring charging to take place.
1.    Use the manual close and open 
controls (refer to Figure 6: Low-voltage 
compartment on page 19) to first close 
and then open the circuit breaker 
contacts. Verify contact positions 
visually by observing the OPEN/CLOSED 
indicator on the circuit breaker.
2.    Open control power circuit by opening 
knife switch shown in Figure 6: Low-
voltage compartment on page 19.
3.    Repeat the spring discharge check 
presented on page 18.
4.    Verify the springs are DISCHARGED 
and the circuit breaker primary 
contacts are OPEN by observing the 
indicator positions.
Final mechanical inspection and testing 
without control power
Before the circuit breaker is energized, it 
must be thoroughly inspected and tested. 
Correct any deviations before energization.
20