Commissioning
4.2 Commissioning with the IOP
SINAMICS G120D converter
Getting Started, 07/2016, FW V4.7 SP6, A5E38556189B AA
63
For performing the basic commissioning of the converter with the IOP operator panel,
proceed the following steps:
Select "Basic Commissioning..." from the Wizards
menu.
Select "Yes" or "No" to a factory reset.
The factory reset is performed prior to saving all the
parameter changes that have been made during the
basic commissioning process.
Select the Control Mode for the attached motor.
Select the correct Motor Data for your Inve
rter and at-
This data is used to calulate the correct speed and di
s-
played values for the application.
Select the correct frequency for your Inver
ter and at-
The use of the 87 Hz characteristic allows the motor to
operate at 1.73 times of its normal speed.