5 Mounting and Installation SMA Solar Technology AG
18 MC-BOX-6_12-BE-en-20 Operating Manual
Procedure:
1. Remove all fastening screws from the kick plates at the front and rear.
2. Set the screws aside. These screws will be needed later to reattach the kick plates.
3. Remove the kick plates and set them aside.
4. Slide the fork of the lift, pallet truck or crane underneath the Multicluster Box and transport the
Multicluster Box to the mounting location.
5.2.3 Installing the Multicluster Box 12.3
1. Mark the positions of the drill holes for attaching the base.