6 Electrical Connection SMA Solar Technology AG
28 MC-BOX-6_12-BE-en-20 Operating Manual
Procedure:
1. Prepare the connection cables (see Section6.2 "Preparing the Cables", page24).
2. Connect the grounding conductor and N to the terminal X3 PV-System as labeled.
3. Connect L1, L2 and L3 to the terminal X3 PV-System as labeled.
6.3.4 Connecting the Sunny Island
Fuse of the Sunny Island inverters
Each Sunny Island is fused by a circuit breaker inside the Multicluster Box.
Multicluster Box 6.3-11: 40 A
Multicluster Box 12.3: 32 A
Optimum mounting location
If the Multicluster Box and the Sunny Island inverters are operated under different ambient
conditions, the circuit breakers for the Sunny Island inverters may trip more often.
To ensure optimum operation, mount and install the Multicluster Box and the Sunny Island
inverters at the same location.