INSTALLATION
UNLOADING, CRANING AND POSITIONING
1. Pre checks
Check 5m clearance of product’s active
area. Any collision anticipated MUST be
avoided!
Check exact positions of cable tubes for
AC connection and wind sensor cabling.
Check positions and dimensions of
mounting bolts in concrete basement and
horizontal alignment with water level.
In case of using earth screw foundation
check positions and height levels.
Check wind sensor position (outside 5 m
active area) and cabling (max 10 meter).
In case of using a dierent mounting pole
than included in the scope of delivery,
ensure that the outer diameter is 50mm.
2. On the truck remove the plastic packing
and check for transport damages (scratch-
es and bumps on the dome, the sidecovers,
solar panels frontglass and siderails).
3. Unloading
a) Unloading by using a fork lift only from
aside position allowed using the dedicated
fork lift supporting holes at the product’s
bottom
b) Unloading and positioning with crane
Important note: Use the transportion guide
as crane hook!
Double function of transportation guide
Refer to chapter 02 – page 14
Installation