INSTALLATION
Installation
ENGLISH
www.stiebel-eltron.com DHB-E SLi | 25
9.3 Appliance with adjustable connected load
The appliance DHB-E 18/21/24 SL is set to 21kW when delivered.
If the appliance is to be installed with a different output, take the
following steps:
Plug in the coding card according to the selected output; for
selectable output and fuse protection of the appliance, see
chapter “Installation/ Specification/ Data table”.
Tick the selected output on the type plate. Use a permanent
marker for this.
Install the flow limiter with an output corresponding to that
of the appliance (see chapter “Installation/ Specification/
Data table”).
D0000047341
10. Installation
Standard installation
- Electrical connection from below on unfinished walls
- Water connection on unfinished walls
For further installation options, see chapter “Installation/
Installation options”:
- Electrical connection from above on unfinished walls
- Electrical connection on finished walls
- Large conductor cross-section for electrical connection from
below
- Connecting a load shedding relay
- Water installation on finished walls
- Water installation on finished walls with solder/ compres-
sion fitting
- Water installation on finished walls; fitting the appliance
cover
- Fitting the base part of the back panel with threaded fittings
on finished walls
- Wall mounting bracket when replacing an appliance
- Installation with offset tiles
- Pivoting appliance cover
- Temperature limit / Anti-scalding protection
10.1 Standard installation
Opening the appliance
26�02�02�0808
Open the appliance by pulling the flap forwards and down-
wards, undo the screw and lift up the appliance cover.
26�02�02�1101
Remove the back panel by pressing the two locking hooks
and pulling the base part of the back panel forwards.
Preparing the power cable
30
1
26�02�02�0824�
1 Installation aid
Prepare the power cable.
Fitting the wall mounting bracket
D0000059694
Mark out the holes for drilling using the installation template.
If the appliance is to be installed with water connections on
finished walls, also mark out a fixing hole in the lower part
of the template.
Drill the holes and secure the wall mounting bracket at 2
points using suitable fixing materials (screws and rawl plugs
are not part of the standard delivery).
Fit the wall mounting bracket.