INSTALLATION
Preparation
12 | WPL-A Premium www.stiebel-eltron.com
9.6.2 Installation on strip foundation
Strip foundation
B
C
A
1
3
2
100100
D0000100624
A 1160
B 650
C 490
1 Air intake side
2 Air discharge side
3 Main wind direction
f Erect a strip foundation at ground level.
f Lay the condensate drain pipe.
f Fill in with gravel up to the top edge of the strip foundation.
Installation on strip foundation
12
6
A
B
5
4
3
D0000100623
A 300
B Depth of frost line
1 Heating flow
2 Heating return
3 Strip foundation (edge block)
4 Rubble
5 Condensate drain conduit
6 Gravel bed
Note
To secure the appliance against toppling over, it can also
be fixed to the foundations with screws.
f Use the accessories with which the appliance was
secured to the transport pallet.
D0000064201
f Hook two brackets respectively into the lateral slots on the
front and back. Ensure you are using the correct brackets for
the left and right hand slots respectively.
f Position the brackets so that the groove on the bracket is
hooked into the appliance.
f Secure the appliance to the foundations using the brackets
and suitable rawl plugs and screws. Do not use the screws
with which the appliance was secured to the transport pallet.
9.6.3 T-support SK1
Note
f Install a ribbon heater when mounting on the wall
bracket or T-support (see chapter "Electrical connec-
tion/ Ribbon heater").
A
B
8
5
7
3
4
2
1
6
9
10
D0000050006
A Depth of frost line
B 300
1 Heating flow
2 Heating return
3 Conduit for supply line
4 Foundation
5 T-support
6 Gravel bed
7 Condensate drain conduit
8 Condensate drain
9 Ribbon heater
10 Cover