Strasbaugh Preventive Maintenance Schedules
Version 4.0 - February 1998 8 - 7
7-DAY PREVENTIVE
MAINTENANCE SCHEDULE
SUBJECT ACTION
Slurry Distribution Lines
Slurry Storage Tanks
Slurry System
Table Coolant Inlet, Outlet Gauges
Table 1
Two Table Shuttle Assembly
Under Polish Table, on Floor
Check slurry distribution lines for
condition and leaks; replace as needed.
Drain, wipe out, rinse out filter screen,
and reassemble.
Clean and check slurry pumps and motor
panel.
Ensure pressures are correct on table
coolant inlet and outlet gauges.
Clean and check splash ring, table top
and sides, and back shield.
Clean and check:
Load chucks, load rings, load station tray,
table top and sides, table pan, and top,
middle, bottom shuttle plates.
Check slurry distribution lines for
condition and leaks; replace as needed.