SH5K+_GD_Quick Commissioning Guide_201803 Page 3 of 3
Once the commissioning is completed, please follow the below procedures to test the
system. (Note: below photos only show as an example)
The inverter only shows green light ON and status shows Running; if the existing
solar power is sufficient, the system should charge the battery.
Turn more load ON to see whether the battery discharges.
If the EPS box (or backup) is installed, turn off the grid supply main to test the Off-
grid function; if the function is OK and then turn the grid supply main to ON.
After completing these testing, the system should run OK.
For any assistance, please contact Sungrow Service Department.