EasyManua.ls Logo

Sungrow SH5K+ - System Testing Procedures; Verify Battery Charging Status; Test Battery Discharge Operation; Test Off-Grid Mode

Sungrow SH5K+
3 pages
Print Icon
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
!
Sungrow Australia Group Pty. Ltd. | 1800 SUNGROW (786 476)
service@sungrowpower.com.au | www.sungrowpower.com.au
SH5K+_GD_Quick Commissioning Guide_201803 Page 3 of 3
Once the commissioning is completed, please follow the below procedures to test the
system. (Note: below photos only show as an example)
The inverter only shows green light ON and status shows Running; if the existing
solar power is sufficient, the system should charge the battery.
Turn more load ON to see whether the battery discharges.
If the EPS box (or backup) is installed, turn off the grid supply main to test the Off-
grid function; if the function is OK and then turn the grid supply main to ON.
After completing these testing, the system should run OK.
For any assistance, please contact Sungrow Service Department.

Other manuals for Sungrow SH5K+

Related product manuals