9
• Push the rubber hose from the system kit (SK-FTG-K) over the panel header as per diagram Step 3d. Slide a
metal collar (SK-FTG-L) onto the rubber hose. Place metal collar
1
/
4
" from edge and tighten collar with
screwdriver. See Fig 3c-1. Repeat for other end of panel.
• Slide another metal collar onto the rubber hose. Connect the 2 panels together by pushing the rubber hose
over the second panel header. Tighten metal collar to secure assembly. See Fig 3c-2. Repeat for other end of
panel.
• Repeat previous 2 steps for each subsequent system
• Install mounting kits as per instructions included with them. Panels must be installed with a slight
slope (minimum 1 inch per 10 feet) toward the inlet. This will allow the panel to drain properly.
Note: The inlet must always be at the lower end of the panel and the outlet at the higher end of the panel.
Note: A maximum of 12 2ft panels (12 systems) may be plumbed in parallel
• For high wind areas you can install the Nylon straps and Vinyl straps from System Kit.
Mark a spot 6" to the right of the outlet. Mark spots 6" to the right of every second
rubber hose that are on the same side as the outlet. Mark a spot 6" to the right of the
cap. See Fig 3d-4. Place mounting base (SK-RMK-BASE) on these spots. Drill pilot
holes, apply silicone roof sealant and screw mounting base into roof. See Fig 3d-5.
Wrap a Nylon strap (SK-RMK-ST-N32) around the panel header (see Fig 3d-7) or
around rubber hose (see Fig 3d-6). Lay both ends of strap in the mounting base and
pull tight. See Fig 3d-8. Screw on mounting cap.( SK-RMK-CAP). See Fig 3d-9.
Repeat process on the inlet side of the panels but using the Vinyl straps (SK-RMK-ST-V32)
instead.
Fig 3d-6Fig 3d-5Fig 3d-4
Fig 3d-7 Fig 3d-8 Fig 3d-9