INSTALLATION FINAL CONFIRMATION
Electrical 
safety inspection
Check whether the power supply voltage complies with specification.
Check whether there is any wrong or missing connection between the 
power lines, signal line and earth wires.
Check whether the earth resistance and insulation resistance comply with 
requirements.
Installation 
safety inspection
Confirm the direction and smoothness of drainage pipe.
Confirm that the joint of refrigerant pipe is installed completely.
Confirm the safety of outdoor unit, mounting plate and indoor unit
 installation.
Confirm that the valves are fully open.
Confirm that there are no foreign objects or tools left inside the unit.
Complete installation of indoor unit air inlet grille and panel.
Refrigerant 
leakage detection
The piping joint, the connector of the two valves of the outdoor unit, the 
valve spool,  the welding port, etc., where leakage may occur.
Foam detection method: 
Apply soapy water or foam evenly on the parts where leakage may occur, 
and observe whether bubbles appear or not, if not, it indicates that the 
leakage detection result is safe.
Leak detector method: 
Use a professional leak detector and read the instruction of operation, 
detect at the position where leakage may occur.
The duration of leak detection for each position should last for 3 minutes 
or more; 
If the test result shows that there is leakage, the nut should be tightened 
and tested again until there is no leakage; 
After the leak detection is completed, wrap the exposed pipe connector 
of indoor unit with thermal insulation material and wrap with insulation 
tape.
Do the following checks before test run.
Inspections Before Test Run
Description
Inspection method
32