Page 4 of 12
Installation steps
Step 1 : Review the whole structure and choose the proper installation site
Choose a solid flat level ground area to set up the building. Do not install the
building on soft ground, wetland, uneven surfaces, sloped surfaces.
We strongly recommend that you build the structure on a solid foundation such as
cement and use anchor bolts on all base plates.
Be aware of the surrounding area. Do not set up the building near snowdrifts, open
flames or exposed electrical wires. Do not keep heat sources near the fabric cover.
Keep the building surroundings clear at all times
Mark the ground in the final building location with a line showing the positions of
base plates, front doors. All lines should be drawn from center to center of all base
plate tubes. Diagonal line X must be equal to Y.
Base plates: all base plates must be installed firmly with expansion bolts (6B) on
this step (refer to figure 1).
Parts used in this step :