Q9 ASD Installation and Operation Manual 25
Startup and Test
Before turning on the ASD ensure that:
The enclosure door is closed or reattached, and secure.
R/L1, S/L2, and T/L3 are connected to the 3-phase input power.
U/T1, V/T2, and W/T3 are connected to the motor.
The 3-phase input voltage is within the specified tolerance.
There are no shorts and all grounds are secure.
All personnel are at a safe distance away from the motor and/or the motor-driven equipment.