UNT-SVX07B-EN 43
Installation—Mechanical
Perform the following procedure to set maximum water flow through the coil:
1. Establish water flow through the coil. Perform an open override of the valve if the control valve
is closed to the coil, either manually or by Tracer.
If the piping package has two-position, normally closed valves: Drive open the valve using a
24 V signal.
If the piping package has two-position, normally open valves: Manually drive open the valve
by removing power to the valve.