Completing the Installation
IImmppoorrttaanntt:: BEFORE COMPLETING THE INSTALLATION, YOU MUST PERFORM THE FOLLOWING PROCEDURES IN
ACCORDANCE WITH THE THERMO KING INSTALLATION STANDARDS AND PROCEDURES GUIDE (TK
56430):
SYSTEM EVACUATION PROCEDURES
SYSTEM LEAK CHECK PROCEDURES
SYSTEM CHARGING PROCEDURES
CONFIGURATION SOFTWARE PROCEDURES
CONTROLLER PARAMETER SETUP