WehoPuts 5
WehoPuts 10
WehoPuts 5
2.3.3 Anchoring and
installation of treatment plant
The treatment plant is delivered
with a ready-made anchoring
package, including 8 anchoring
plates and 2 anchoring rods. The
anchoring rods are installed before
the treatment plant is lowered into
the trench. Anchoring is especially
important in locations where the
soil contains mostly clay or high
groundwater levels.
Lower the treatment plant
into the trench using the
li ing rings.
Install the anchor plates
(4 pcs/rod) on the rods inside
the trench.
Fill in the trench in layers,
constantly compacting (grain
size max 20mm) to the level
of the inlet spigot.
WehoPuts 10
Install the anchor rods
through the holes at the
bottom of the tank (see
picture).
WehoPuts 5
Install the anchor rods
through the holes in the
treatment plant bottom ribs
on each side of the unit.
9

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Uponor WehoPuts Series and is the answer not in the manual?

Uponor WehoPuts Series Specifications

General IconGeneral
BrandUponor
ModelWehoPuts Series
CategoryWater System
LanguageEnglish

Related product manuals