5000/10000 FLYWHEEL GRINDER
MACHINE SET-UP
1. Remove protective covering from around machine. Remove bolts from four corner pads to
free machine from skid. Remove all tooling packages from machine and set aside. Using
the fine feed handknob, raise the grinding head motor off the wood shipping block and
discard. Unlock the grinding head column lock handle (Figure 1) and swing the grinding
head motor so it is centered over the table. Relock the motor flange.
Figure 1
2. A forklift is recommended for removing the machine from the skid and setting in place. Lift
only from the base cabinet from the rear (Figure 2).
Figure 2
Van Norman 18. 888-855-1789