n The drain is placed in a floor recess and then cast-in.
During the mounting on the floor, the drain is integrated into the floor
construction. At the same time, it can e.g. be integrated into the level‐
ling screed or heat insulation. If necessary, a vertical drainpipe can be
led through a drill hole in the floor at the same time.
NOTICE!
The creation of a floor recess must be agreed with the fol‐
lowing people:
– a structural engineer
– the on-site fire protection inspector or the specialist
engineer for fire protection
If necessary, proof of compliance with building code or an
expert's report must exist.
Fig. 1: General installation example – Floor
recess
Mounting on a floor
Fig. 2: General mounting example – Mounting
on the floor
Product information