Operation
Continued from the previous page.
Purging the
oil discharge
line
Perform the procedure below to purge the oil discharge line.
1. Locate the oil discharge line (c).
2. If air bubbles are visible in the oil discharge line, they must be manually purged
using the following method:
Disconnect the oil discharge line at the oil pump (d). Using a plastic syringe (e)
filled with oil, inject oil into the oil discharge line until the air bubbles are gone
and oil is visible up to the carburetor adapter fitting (f).
3. After the air bubbles have been purged, reconnect the oil discharge line. Make
sure that the connections are tight with no oil leaks.
4. Wipe residual oil from the oil discharge line and fittings.
Result
The oil lines have been purged.
wc_gr012472
c
c
e
f
d

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Wacker Neuson BS70-4As and is the answer not in the manual?

Wacker Neuson BS70-4As Specifications

General IconGeneral
BrandWacker Neuson
ModelBS70-4As
CategoryConstruction Equipment
LanguageEnglish

Related product manuals