6 Commissioning | Commissioning with the SIMATIC Manager (PROFINET)
26 2547720000/03/09.2019Manual Communication module UR20-4COM-IO-LINK
AddingIO-LinkmasterinSIMATICManager(Example:PROFINET)
Parameterising IO-Link port with SIMATIC Manager
The IO-Link ports are parameterised using the IO-Link master
parameters. An overview of all parameters is presented in
section 4.6.
Double-click the module in the module list.
The UR20-4COM-IO-LINK Properties window opens.
Select the Parameters tab
The list of all parameters is displayed.
Editing module parameters
Click the parameter that you would like to change and
select the desired setting.
Use this method to edit all of the parameters that you
want to change.
Click OK to save the settings.
All settings only take effect once they have been
loaded into the component.
Integrating IO-Link device with SIMATIC Manager
An IO-Link device is integrated using the suitable parameteri-
zation of the associated IO-Link port.
Double-click the module in the module list.
The UR20-4COM-IO-LINK Properties window opens.
Select the Parameters tab.
Set the “Operating mode” parameter of the IO-Link port to
the value “IO-Link”.
Set each of the parameters “Process data length input”
and “Process data length output” to the value “auto”.
Change the other parameters as required.
Save the setting by clicking OK.
All settings only take effect once they have been
loaded into the component.