3. Connect the drain to the outside stem
4. Connect the product to the center stem
5. Connect the inline water coming from the Pre-Carbon through the ASO into
the input
a. Connect the source line to the source on the outside of the filter box
b. Connect the drain to the drain on the outside of the filter box
c. Connect a secondary drain to the top of the TCR
d. Turn the water on for 30 minutes or greater
6. With 60 PSI going into the system after 30 minutes your TDS should be
reduced approximately 98 percent after the RO membrane vs the incoming tap
TDS.
7. The TDS after the TCR filter should only be 5-8 points higher
a. As the system is flushing during each step inspect for any leaks and/or
loose connections
8. Sanitize the ice Bin and water reservoir
a. Remove the top lid by removing two screws on the back side of the top
panel
b. Remove the top panel
c. Remove the front panel by removing two screws found behind the drip
tray
d. Remove the ice and water spigots
e. Slid the front panel off
f. Remove the screws to be able to access the ice tank
g. Remove the lid to the ice tank with the insulation included
h. Remove the stainless-steel augers and the plastic bottom to the ice
tank
i. Spray the inside of the tank with hydrogen peroxide and wipe out with a
clean paper towel
j. Hydrogen peroxide should be approximately a 20 percent Hydrogen per
oxide to 80 percent water blend
k. Spray the plastic bottom with the same blend along with the stain
less-steel augers.
l. Reinstall the plastic bottom and the augers
m. Do one more light spray of hydrogen peroxide and put the top back on
along with the insulation and screws
n. Remove the lid to the water reservoir
o. Spray the inside of the reservoir in the same way and wipe out
p. Spray a light mist and then put the lid to the reservoir back on
q. Re-install the front panel and the top panel
Installation Guide (cont.)
04
09
9. Connecting the Filters to the WS 15000 (a 3 to 4-gallon bladder tank must
be used as well)
a. Mount the filter enclosure under the sink
b. Attach the supply line to the water Supply input on the filter enclosure
c. Attach the RO drain line to the RO drain connection on the filter enclo
sure
d. Connect the feed line from the filter enclosure to a T
e. Connect the T also to the bladder tank
10. Ensure that the pressure of the bladder meets the manufacturers recom-
mended pressure before allowing it to fill
a. You will then hear the compressor and the auger running
b. Please wait about 30-60 minutes for ice to be used after it starts
making ice
c. You must wait until the hot tank completely fills before turning on the
hot water switch which is located on the back of the system behind the
caution sticker (lower right side)
Note: In order to insure reliability and the highest performance only genuine
Wellsys filters should be used and must be changed on time. Please reference
below for the filter change schedule.
1. Pre-Sediment Filter 1 year or 2500 gallons max
2. Pre-Carbon filter 1 year or 2500 gallons max
3. Reverse Osmosis 3 years or 4500 gallons max
4. BIO-Sure Plus 1 year or 750 gallons
5. TCR 2 years or 2500 gallons
6. Air filter 2 years in office environment
Filter schedule is only an estimate and does not guarantee the life will last to
this length of time. Many factors may impact the life of each filter including
but not limited to poor water quality, low pressure, incorrectly installed and
neglect.