5.1.6 Mounting the instrument
The max. torque depends on the mounting point (e.g. material and shape). If you have any questions,
please contact our application consultant.
→ For contact details see chapter 1 “General information” or the back page of the operating instructions.
If a process connection adapter (optional) is used, rst screw it into the mounting point by hand and then tighten it
using a torque spanner. Use enclosed sealing.
1. Depressurise the system and switch o the ow.
2
.
Seal the process connection (→ see “Sealing variants”).
3
.
At the mounting point, screw the ow switch in hand-tight.
4
.
Tighten with a torque spanner using the spanner ats.
5.2 Electrical mounting
Requirements for voltage supply
Power supply: DC 15 ... 35 V
The power supply for the ow switch must be made via an energy-limited electrical circuit in accordance with section
9.3 of UL/EN/IEC 61010-1 or an LPS to UL/EN/IEC 60950-1 or class 2 in accordance with UL1310/UL1585 (NEC or
CEC). The voltage supply must be suitable for operation above 2,000 m above sea level, should the ow switch be
used at this altitude.
Requirement for shielding and grounding
The ow switch must be shielded and grounded in accordance with the grounding concept of the plant.
The instrument must be grounded via the process connection.
Connecting the instrument
1. Assemble the mating connector.
→ see pin assignment
2
.
Establish the plug connection.
5. Commissioning, operation