13
3062049_201610
KG TopInstallationinstructions
Sealant
Immediatelybeforeassemblingtheverticalhollowsectionswiththeoorandceiling
panels, seal the hollow sections with the sealant supplied. Otherwise the water tightness
of the appliance cannot be guaranteed.
For this it is recommended that some of the sealant is poured into a at vessel of
adequatesize,andthentodipbothendsoftheverticalhollowsectionapprox.2mm
deep into the sealant.
The appliances are assembled in reverse order.
Appliancesthatcan
bedismantled
The equipment is shipped to site preassembled. It can be disassembled before being
movedintopositionandreassembledatthenallocation.
Disassembly entails removing the casing and carefully removing internal components
such as heating or cooling coil (take care not to damage the components). Remove the
screws from the corners of the frame to permit removal of the frame.
Undo
screws
KG Top 21 - 380 KG Top 450 - 1000
Hollow
prole