62 support@yardistrystructures.com
PLACE A SILICONE SEAL at TOP where the ROOF PEAK and
ROOF VENT PEAK join as shown by the darkened line
See page 6 for Warning and
First Aid Information.
PLACE A SILICONE SEAL at TOP where the ROOF PEAK and
ROOF VENT PEAK join as shown by the darkened line
Step 14: Attach Roof Assemblies to Frame
Part 3
E: Apply silicone sealant at top of assembly
where (1123) Roof Peak and (1124) Vent Roof
Peak join. Sealant should be applied in small
beads and smoothed out. (F14.9 and F14.10)
F: Apply silicone caulking on the top of the
Continuous Hinge so the silicone complety
covers the pivot joints. (F14.11)
F14.9
F14.10
Components
Sealant
(1124) Vent
Roof Peak
(1123) Roof
(1124) Vent
Roof Peak
(1123) Roof
Sealant
Note: All surfaces to be clean, dry, dust
and grease free before application with
temperatures above 5
°
C (41
°
F), no warmer
than 35
°
C (95
°
F).
•
then put in caulking gun. See page 6.
• Apply sealant in small beads and smooth
as required.
• Clean excess with a cloth or paper towel
before it skins over.
• Always wear safety glasses and rubber
gloves when using product.
F14.11
Sealant
Continuous
Hinge