11. Right-click on network 1 and select Network (after)
ð
You added a network “2” below network 1.
Add assignments and a Boolean NOT to the DO signals
1. Add an assingment from the Tools.
2. Type in or copy & paste "xDrillerBroken1" to the left side of the instruction line.
3. Select “???” on the right side of the instruction line, then press F2.
ð
“Input Assistant” opens.
4. Under “Global Variables” open “DA501_Module_Mapping”
5. Select “xStartDrilling1”
6. Select [OK] to close the dialog.
7. Right-click the left side of assignment PIN.