Operation Manual / 4 Product description / A150-M.. - A155-M..
8
Dismantling and fitting
Page 81 /
120
© Copyright 2017 ABB. All rights reserved.
HZTL4032_EN
Revision F
January 2017
Removing the cartridge group
Figure 37: Removing cartridge group 1
Product
Dimension X
A150 112 ±2 mm
A155 144 ±2 mm
Table 37: Threaded rod, dimension X
1. Apply two marking lines (M) to the left and right of the cartridge group and the bracket.
2. Support and fix the turbine casing.
3. Loosen the clamping nut (42201) (see Loosening the clamping nut [➙ 12]).
4. Screw threaded rod (42191) up to value X at the hexagon.
5. Lift the centering bush (42193) using the threaded rod (42191) and hold it firmly.
If the centering bush jams:
Remove the clamping nut and rotate the threaded rod upwards using a standard nut.
6. Rotate the clamping nut (42201) downwards until the stop is reached.