Lists the specific tools needed for the softstarter upgrade procedure.
Specifies the necessary LV and HV board versions for Torque Control upgrades.
Steps 1-10: Mark and disconnect cables, remove front cover, and uninstall old HV/LV boards.
Steps 11-15: Install new LV board, connect display/keypad, and manage PSTB by-pass connections.
Steps 16-21: Install new HV board, connect thyristor/fan cables, and verify current transformer connections.
Steps 22-23: Re-mount front cover and reconnect all external power and control cables.
Steps 1-4: Power on, navigate to Service Settings, confirm, and set the display language.
Steps 5-9: Set CT Ratio Ir, Int ByPass, ByPass AC3, SOP parameters, and PST(B).
Steps 10-12: Confirm programming, set motor current/protections, and consult further documentation.