Operating procedures for the PC aided methods of changing the active setting
groups are described in the corresponding PCM600 documents and
instructions for the operators within the SCS are included in the SCS
documentation.
9.14.1.2 Completing the test
M11369-39 v4
Continue to test another function or end the test by changing the TESTMODE
setting to Off. Restore connections and settings to their original values, if they were
changed for testing purposes.
9.15 Exit test mode
SEMOD53244-3 v5
The following procedure is used to return to normal operation.
After exiting the IED test mode, make sure that the MU is returned
to normal mode.
1. Navigate to the test mode folder.
2. Change the On setting to Off. Press the 'E' key and the left arrow key.
3. Answer YES, press the 'E' key and exit the menus.
1MRK 506 383-UEN A Section 9
Testing functionality by secondary injection
Line distance protection REL650 2.2 IEC 171
Commissioning manual

Table of Contents

Other manuals for ABB REL650

Related product manuals