Operation Manual / TPL65-A32 / -A33 / -A36 + TPL69-A32 / -A33
5 Maintenance / 5.3 Cleaning the compressor during operation
© Copyright 2020 . All rights reserved. HZTL2498_EN Rev.F December 2020
5.3.2 Wet cleaning using external water-pressure vessel
(XC3)
Operating state prerequisites for wet cleaning XC3
NOTICE
To be able to carry out a satisfactory cleaning process which has been
tested and is recommended by ABB Turbocharging, the following pre-
requisites must be fulfilled:
u Engine load 50 … 85%
u Start of cleaning cycle in accordance with following description for
wet cleaning operation with XC3.
Operating procedure for compressor wet cleaning with XC3
Operating the water pres-
sure vessel
u The operating state prerequisites for compressor cleaning with XC3
must be fulfilled.
u Remove sealing plug (X).
u Fill vessel with required volume of clean water (see table Cleaning
parameters).
u Screw in sealing plug (X).