6. Assembly of the switchgear at site
Figure 126:
1 Top mounted box with voltage transformer
2 Hexagonal shaft
3 Reducer ring
4 Intermediate box
5 Partitioning
Figure 127:
1 Top-mounted box
2 Hexagonal shaft
3 Reducer ring
4 Intermediate box
5 Pressure relief flap
6 Connection bar
24 kV panels - Arrangement of the busbar and branch conductors at the busbar ends. In
continuous busbars, the connections are similar, but without the lid holder and without the spacer plate.
Panels 12 / 17.5 kV - Top-mounted box with voltage transformers for busbar metering.