7 - Operation
Once the meter model is selected, additional requested
elds will appear:
- METER PHASE: If the METER is three-phase, the
phase to which the inverter is connected must be
selected. (This eld will appear only if you select
the ABB B23 3PH meter model)
- ENERGY POLICY: set the way in which you want
to manage the energy produced by the PV plant,
choosing from the following:
Management
mode
Description
Self
consumption
The system automatically mana-
ges power ows in order to maxi-
mise self-consumption. All unused
power from domestic loads will
feed into the grid.
Zero injection
The system automatically mana-
ges power ows in order to avoid
the injection of energy to the grid.
If the meter is disconnected or not
working the inverter's output po-
wer is restricted to zero in order to
avoid accidental power feeding to
the grid.
Congurable
The system automatically mana-
ges power ows in order to avoid
feeding the grid with power greater
than:
P
DC
x P
lim
where P
DC
is the power of the pho-
tovoltaic generator (“PV GENE-
RATOR POWER” parameter) and
P
lim
is the output power limit with
respect to P
DC
(%) (“FEED-IN PO-
WER” parameter).
- PV GENERATOR POWER: Insert the power value
of the photovoltaic system (kWp) installed.
- FEED-IN POWER: Set the percentage AC po-
wer restriction (with reference to the value of the
photovoltaic system (kWp) installed) to be feed into
the grid. This eld can be edited only if the Energy
Policy selected is “Congurable”.
Conrm the settings by clicking “END” and the inverter will
test the meter working (if selected a meter device) and it
will reboot at the nish of test phase.