5. Commissioning Procedure
After all the cable (power and communication) connections are completed, please ensure
the following:
Ensure the DC switch on the inverter is OFF
Ensure the AC switch that is connected to the grid and EPS output (if used) of the
inverter is OFF
Ensure the DC switch is OFF
For commissioning we recommend the following steps:
Turn the DC switch ON
Refer to
section 3.3.2 Start for turning on the battery
Wait until the LED´s on
Wait until the inverter LED´s on
Storage
Environment
Temperature
Relative Humidity of
Storage Environment
Storage Time
SOC
Below - 10
/ Prohibit /
-10~25
5%~70%
12 months
SOC
60%
25~35
5%~70% 6 months
SOC
60%
35~45
5%~70% 3 months
SOC
60%
Above 4 5
/ Prohibit /
Recharge Requirements During Normal Storage
Battery should be stored in an environment with temperature range between -10°C ~ +45°C
and maintained regularly according to following table with 0.5C(50A) current till 50% SOC
after long storage time.
Storage
Environment
Temperature
Storage Time
Note
-10~25
15 days
Battery Pack
disconnected to inverter
25~35
7 days
35~45
<12 hours
Battery Pack
connected to inverter
Recharge Requirements When Over Discharged
Over discharged (90%DOD) battery should be recharged according to following table,
otherwise over discharged battery will be damaged.
6. Maintenance
Fault
Normal
Fault
Normal
Fault
Normal
Fault
Normal
Turn on the DC switch on the inverter
Set up the battery and the inverter on the App
Turn on the AC switch that is connected to the grid and EPS output of the inverter