9.4. SETTLE THE BENDING MATERIAL
You can begin the bending operation,after all the control operations.
The first step of the bending operations,is the place of the bending material.
The stright position of the material tighten between the top rolls,is initial condition for the good
quality bending material.
The step for this operations.
1-The bending material,absolutely must place between the top rolls.
2-The bending material,absolutely must be paralel to the top rolls axis.
9.5. BENDING OPERATION
The first operation is giving the machine power. The other operations are following.
1- Turn the power switch to position 1 rear the face electrical panel.
2- Check the power lamp is lighting or not. If the lamp is not lighting,check the
electrical connections..
3- Press the start button.
The machine is ready to working.