INSTALLATION
Vecto r H® S eries ▪ Opera tor’s Manual ▪ M N-462 9 5 ▪ Rev 6 ▪ 1/22
22
Continued from previous page
Continued on next page
Electrical
Alto-Shaam oven ratings Breaker: Voltage: Phase:
The following fields must be completed by the service technician on site.
What is the measured voltage at the site? L1-N: L2-N: L3-N: L1-L2:
L2-3: L1-L3: Pass Fail
What is the on-site breaker size supplying
power to the oven(s)?
Size: Pass Fail
Is there a disconnect or junction box within
3’ (914mm) of where the oven(s) will be
installed?
Pass Fail
Comments:
Gas-F Series only
What is the gas type for the oven(s) to be installed? Natural Propane
What is the gas type confirmed at installation site? Natural Propane Pass Fail
Is there a minimum of one 3/4” gas supply line within 3’
(914mm) of where the oven(s) will be installed?
Pass Fail
On the gas line, is there a 3/4” NPT pipe connection with a
shut-off valve within 3’ (914mm) of where the oven(s) will be
installed?
Pass Fail
Comments:
Wi-FI equipped ovens
Is the Wi-Fi system that be used secure, Wi-Fi Protected Access 2 (WPA2)? The
Wi-Fi system to be used cannot be Point of Sales Wi-Fi.
Yes No
Have you been provided the Service Set Identifier (SSID) for the system to be
used?
Yes No
Have you been provided the password for the Wi-Fi system to be used? Yes No
At the final location that the oven will be installed, can you connect to the Wi-Fi
system with your phone?
Yes No
At the final location that the oven will be installed, can you connect to
Alto-Shaam.com with your phone using the Wi-Fi system?
Yes No
Is site action required? Yes No
Action required: